Maldives Transport and Contracting Company (MTCC) has provided an update on the progress of the construction of R. Angolhitheemu harbor.
MTCC Thursday said the project has now reached 53 percent completion. The installation of harbour pavements over an area of 1,110 square meters is now complete, the company said.
The scope of the project includes dredging and excavation operations of 42,615 cbm; construction of a 221m breakwater; a 166m revetment; a 91m quay wall; installation of 1110sqm paved area, installation of streetlights and navigation lights. The value of the project is MVR 40.7 million.