Hoarafushi sewerage network inagurated

President Abdullah Yameen Abdul Qayyoom has launched the sewerage network of Ha. Huvarafushi today.

The project is a state sponsored project carried out by Male' Water and Sewerage Company (MWSC). The project began on November 4, 2014 and concluded on December 31, 2015.

A total of MVR 60,036,031.05 had been spent on the project. At the completion of the project, four pump stations, 14.94 km of sewerage network and a sea outflow pipe measuring 256 meters had been created in the island.

Due to the new network, all homes in the island will be covered in a proper network.

Hoarafushi sewerage network

  • Total cost of project: MVR 60,036,031.05
  • Number of pump stations: four
  • Sea outflow number: one
  • Length: 256 meters
  • Number of man holds: 382
  • Number of houses covered in the network: 671