MTCC completes 47% of Komondoo harbour project

Maldives Transport and Contracting Company (MTCC) has completed 47% of the harbour project of the island, Sh. Komandoo.

According to the contractor MTCC, currently, the work of sea wall construction is ongoing, and 47% of the project has been completed.

The contract was awarded to MTCC in August last year. According to MTCC, the practical work of the project began in December after concluding Environmental Impact Assessment.

A 12-meter breakwater, 20-meter revetment, and a seawall are being constructed under the project. Installing street lights and the pavement of the harbour area is also included in the project.

The value of the project is MVR 29.4 million.

MTCC has been working on harbour and reclamation projects of several islands of the Maldives. Some of the projects have been completed over the past three months.